REGINA · BATHROOM RENOVATION CASE STUDY

A tub-to-shower conversion that started beneath the floor.

A Regina bathroom needed more than a new shower. To make the conversion work, Oakridge opened the concrete floor, reworked the shower and laundry drainage, and rebuilt the room around the new layout.
Finished bathroom with a walk-in shower beneath a window, grey floor and white toilet.
Finished · The new shower beneath the existing window

PROJECT AT A GLANCE

Regina, Saskatchewan

Residential bathroom

Tub-to-shower conversion

Drainage, ventilation and a complete bathroom rebuild
Original bathtub and surround beneath the bathroom window before renovation.
Before · The original tub and surround

THE STARTING POINT

A new shower meant looking beneath the slab.

The bathroom began with a bathtub and surround beneath the window. Replacing that tub with a shower involved more than changing the visible fixtures: the existing drainage for the tub and nearby laundry needed to be reworked beneath the concrete floor before the new shower could be installed.

BEFORE & AFTER

From bathtub to shower.

Original bathtub and surround beneath the bathroom window before renovation.
Before · The bathtub and surround
Finished bathroom with a walk-in shower beneath a window, grey floor and white toilet.
After · A new shower and finished bathroom
Where the old bathtub once sat, a new shower now fills the end of the room. New flooring, a vanity and updated lighting complete the bathroom.

What it took to make the change.

Open the floor and rework the drains

The concrete was opened to reroute the old tub and washing-machine drains. New shower and laundry drainage, venting and water lines were installed before the floor was patched. This work happened before the new shower and flooring could go in.

Rebuild the room around the shower

After demolition and plumbing, the exterior wall was repaired and insulated, and new drywall prepared the room for its finishes. A new exhaust fan and duct, recessed lights, switch and receptacle were included in the work.

Finish with the homeowner’s selections

The original quote contemplated tiled shower walls. The finished project used a homeowner-supplied shower surround instead. The supplied flooring and fixtures, vanity, backsplash, trim and paint brought the room together.

THE PROJECT IN PHOTOS

The work behind the finished bathroom.

Bathroom stripped back for renovation, with framing and the window visible.
Opened up · The bathroom after the tub and wall finishes were removed
Opened concrete floor with exposed drain piping and reinforcing during bathroom renovation.
Below the floor · Concrete opened for drainage work
Finished bathroom vanity with a black faucet and framed mirror beside the toilet.
After · Vanity, mirror and finished fixtures

THE RESULT

A new shower, supported by the work you don’t see.

The result is a finished bathroom with a shower in place of the original tub. The change depended on work below the floor as well as the finishes above it: drainage and water lines, a patched slab, wall repairs, ventilation and lighting all had to come together.

Project scope: tub removal, shower and laundry drainage, water lines, concrete patching, exhaust fan and duct, lighting, drywall, homeowner-supplied shower surround and flooring, vanity, backsplash and finishing.

Planning a similar project? Explore our Regina tub-to-shower conversion guide, learn about our bathroom renovations, or try the bathroom budget calculator.

Historical project range: Oakridge’s invoiced work fell in the $15,000–$25,000 range, including tax. The homeowner supplied some materials, so this is not the full project cost. Every renovation is different; the range is historical context, not a quote.

LET’S PLAN YOUR RENOVATION

Planning a tub-to-shower conversion?

Tell us about your bathroom, what you want to change and any questions about the existing plumbing. We’ll discuss a practical next step.
Scroll to Top