REGINA · ENSUITE RENOVATION CASE STUDY

A jetted tub became a shower—with a drain challenge beneath the floor.

Replacing an ensuite bathtub with a shower meant relocating the drain. When the new drain location met a floor joist, Oakridge reworked and supported the framing before installing the new shower.
Finished ensuite shower with a white surround, black-framed glass doors and black fixtures.
After · The completed ensuite shower

PROJECT AT A GLANCE

Regina, Saskatchewan

Residential ensuite

Tub-to-shower conversion

Drain relocation, framing adjustments and bathroom finishes
Original jetted bathtub with a wood-coloured front and tiled floor before the ensuite renovation.
Before · The original jetted bathtub

THE STARTING POINT

A new shower needed a different drain location.

The ensuite began with a jetted bathtub and an existing tiled floor. The renovation called for removing the tub and installing a shower in its place. Once work began on the drain relocation, the team found a floor joist in the required path.

BEFORE & AFTER

From jetted tub to glass-enclosed shower.

Original jetted bathtub with a wood-coloured front and tiled floor before the ensuite renovation.
Before · The original ensuite bathtub
Finished ensuite shower with a white surround, black-framed glass doors and black fixtures.
After · The new shower and glass doors
The tub was removed and the shower installed in the same area. The completed shower combines a white surround and base with black fixtures and glass doors.

The work beneath and around the shower.

Resolve the drain and floor-joist conflict

The new drain location met an existing floor joist. Oakridge opened the floor and restructured and supported the framing so the shower drain could be routed. The work responded to the conditions found in this home.

Build the new shower

New water lines were fitted and the shower pan was set on a mortar bed. Three shower walls and glass doors were installed as the shower area came together.

Finish the surrounding bathroom

Drywall, flooring, baseboards and a vanity backsplash were part of the original renovation. The same scope also included flooring and backsplash work in the hallway bathroom.

THE PROJECT IN PHOTOS

The work behind the finished shower.

Opened bathroom subfloor showing framing and exposed drain plumbing during the shower conversion.
During construction · The opened floor and shower drain
New shower base protected during installation with a wall surround and framing visible above.
During construction · The new base and surround taking shape
Ensuite vanity, mirror and finished flooring after the bathroom renovation.
After · The ensuite vanity area and finished flooring

THE RESULT

A finished shower, built around the conditions beneath it.

The ensuite now has a glass-enclosed shower in place of the original jetted tub. Resolving the drain and joist conflict was an important part of the work before the shower and bathroom finishes could be completed.

Project scope: tub and surround removal, shower drain relocation and framing adjustments, new water lines, a mortar-set shower pan, shower walls and glass doors, drywall, flooring, baseboards and backsplash work. Related hallway-bathroom flooring and backsplash work were also included.

Considering a similar change? Read our Regina tub-to-shower conversion guide or explore our bathroom renovation service.

Historical project range: Oakridge’s invoiced work for the original ensuite and hallway-bathroom work together fell in the $10,000–$20,000 range, including tax. This is not the ensuite-only cost and may not include all homeowner purchases or subsequent work. The range is historical context, not a current quote.

LET’S PLAN YOUR RENOVATION

Considering a tub-to-shower conversion?

Tell us about your existing bathroom, what you want to change and any questions about the space or plumbing. We’ll discuss a practical next step.
Scroll to Top