REGINA · BATHROOM RENOVATION CASE STUDY

Behind the tile, the damage went deeper.

The homeowner suspected water damage near the bottom of the tiled tub surround. Once we opened it up, we found extensive mould and water damage. The entire wall had to be removed and reframed before the bathroom could be rebuilt.

Original white-tiled tub surround before renovation, with visible damage near the lower tiles.
Before · The original tiled tub surround.

PROJECT AT A GLANCE

LOCATION

Regina, Saskatchewan

THE CHALLENGE

Extensive damage behind the tub surround

THE WORK

Remove the entire wall, reframe and complete the bathroom

01 · THE STARTING POINT

A concern near the bottom of the tub.

This homeowner already knew there might be water damage near the bottom of the tiled surround. The original bathroom had a white-tiled tub area, and the lower section showed deterioration.

The concern was real, but the visible area did not reveal the full extent of the damage. That only became clear once we opened the wall. A renovation that included updating the bathroom now also required a much more substantial wall repair.

02 · WHAT WE FOUND

The entire wall had to come out.

The damage extended beyond the lower area that had first raised concern. Opening the wall revealed extensive mould and water damage, and the entire wall had to be removed and reframed.

Close view of dark, damaged wall boards and framing exposed after the original tub surround was removed.
Opened up · The damage behind the tile.
Wide view of the bathroom wall opened during demolition, showing exposed boards, framing and plumbing.
During demolition · A wider view of the exposed wall.
Rebuilt bathroom wall with new timber framing, pink insulation and clear poly before the tub area was finished.
Rebuilt · The new framing before the bathroom was finished.

03 · THE REBUILD

Repair the wall before finishing the room.

With the damaged wall removed, new framing went in before the tub area received its new finishes.

04 · THE FINISHED BATHROOM

The completed bathroom.

The completed bathroom has a white bathtub, a marble-look tile surround and chrome fixtures. The vanity brings together white shaker doors, dark handles, a veined counter and a wide black-framed mirror.

Completed Regina bathroom with a white bathtub, marble-look tile surround, chrome handshower, white curtain and toilet.
Completed · The bathtub and marble-look tile surround.
Completed bathroom vanity with white shaker doors, dark handles, a veined counter, chrome faucet and a wide black-framed mirror.
Completed · The vanity, mirror and lighting.

WHY THIS PROJECT MATTERS

A new surface would not have repaired that wall.

On this project, a cover over the existing tub area would have left the damaged wall behind it. It could have changed what the homeowner saw without carrying out the wall replacement the bathroom needed.

That is why the condition behind the finish matters. The suspected damage near the bottom was only part of what we found once the wall was opened. The repair needed to follow the damage we uncovered.

Find the problem. Repair the damage. Then rebuild.